![]() Wellpoint installation |
Sevenson’s soil mix wall subcontractor, Geocon, completed the construction of the soil mix wall along the perimeter of the site. A total of 321 soil mix wall columns were installed.
![]() Dewatering well points and header pipe used to transfer water to the waste water treatment plant |
Sevenson’s dewatering subcontractor, Griffin, continued the installation of the excavation dewatering system this week. The well points will be used to pump groundwater from the excavation to the waste water treatment plant.
Two-Week Outlook
Sevenson’s dewatering subcontractor, Griffin, continued the installation of the excavation dewatering system this week. The well points will be used to pump groundwater from the excavation to the waste water treatment plant.
National Grid contractors will continue working in Long Island Avenue to address sewer line issues. Work will continue to complete an inspection of the sewer line and conduct any necessary repairs.
General hours of operation will continue to be Monday through Friday, 7:00 AM to 5:00 PM. To maintain the ambitious schedule for the project, beginning Saturday, January 3, for a period of at least two months, work on the site will also be conducted on Saturdays, between 8:00 AM and 6:00 PM.